Highway 246 Santa Ynez River Bridge
Project funding
- Estimated Project Cost: $27.010 million
- Estimated Measure A Funding Amount: $7.7 million
- Estimated Non-Measure A Funding Amount: $19.31 million
- Project Construction Start Date: Fiscal Year 2027/28
- Project Status: Pre construction phase
Status
The project will improve access to Lompoc across the Santa Ynez River by a providing a bridge raised above flood level with wider shoulders that can safely accommodate vehicles, bicycles and pedestrians.
The Measure A Strategic Plan includes $300,000 for the for the development of the Highway 246 Santa Ynez River Bridge Feasibility Study beginning in FY 10/11 with an anticipated completion date of FY 2012/13.
Feasibility Study
- Estimated Project Cost: $300,000
- Estimated Measure A Funding Amount: $300,000
- Estimated Non-Measure A Funding Amount: The project is funded only with Measure A funds
- Project Status: The Feasibility Study is scheduled to begin in Fiscal Year 2010/11